“Summary of Gross and
Net Oil Reserves
|
|
Gross Reserves
(mmbbls) |
Net Amni Reserves
(mmbbls) |
|
|
1P |
2P |
3P |
1P |
2P |
3P |
|
Ima
Oil Field |
3.1 |
6.1 |
10.6 |
3.1 |
6.1 |
10.6 |
|
Okoro
Field |
23.0 |
33.5 |
37.7 |
23.0 |
33.5 |
37.7 |
Summary of Gross and Net Natural
Gas Contingent Resources
|
|
Gross Contingent Resources
(bcf) |
Net Amni
Contingent Ressources
(bcf) |
|
|
1C |
2C |
3C |
1C |
2C |
3C |
|
Ima
Gas Field |
1,132 |
1,602 |
1,914 |
679 |
961 |
1,148 |
Summary of Gross and Net Condensate
and NGL Contingent Resources
|
|
Gross Contingent Resources
(mmbbls)
|
Net Amni
Contingent Resources
(mmbbls) |
|
|
1C |
2C |
3C |
1C |
2C |
3C |
|
Ima
Gas Field |
5.6 |
8.1 |
9.6 |
3.4 |
4.9 |
5.8 |
Summary of Gross and Net Oil
Contingent Resources
|
|
Gross Contingent Resources
(mmbbls)
|
Net Amni
Contingent Resources
(mmbbls) |
|
|
1C |
2C |
3C |
1C |
2C |
3C |
|
Setu
Field |
1.6 |
2.0 |
2.4 |
1.6 |
2.0 |
2.4 |
Note: All reserves and contingent
resources figures are as at 31st December 2008. Source: GCA,
Assessment of Reserves and Contingent Resources in OML-112 and
OML-117, May 2009”
IMA
FIELD
The
Ima field is located in OML 112 and 117 and contains an existing oil
field, which has been in production
since
1996, with current production levels of approximately 1,600 bbls/d.
Redevelopment work will increase production back to around 4,000
bbls/d.
IMA
Oil
Amni
entered into agreements in 2005 under which TOTAL acquired a 40%
interest in OMLs 112 and 117. TOTAL subsequently relinquished its
rights to the crude oil from the presently known reservoirs of IMA
in April 2007. Amni is entitled to 100% of the crude oil from these
reservoirs and bears all royalties and taxes due in relation to
“Ima oil”.
IMA
Gas
Under
the agreement with TOTAL, Amni is carried through the development of
gas reserves (2C: 1.6TCF) until production. TOTAL will then recover
costs out of revenues from gas production.
OKORO/SETU
The Okoro and Setu East Fields are located in OML 112, with the two
fields separated by 6.5km in a water depth of 5m to 14m. TOTAL
relinquished both its right to participate in and any future
development of the Okoro/ Setu fields, allowing Amni and Afren
Energy Resources Limited (as Contractor) to enter into a Production
Sharing and Technical Services Agreement in March 2006, facilitating
field development.
|